Undertaken Projects

A complete list of projects undertaken by EIED is tabulated below:
No Name & Location of Plant Plant Capacity/ Project Description Start & Completion Date Name of the Owner Company’s Scope of Work
 77 SIRAF Condensate Refinery 8 Refineries of 60,000 BPD 2015-2018 SIRAF Condensate Refineries Basic Design (Cooperation with TOYO after 2016.03)
 76 Condensate Refinery 40,000 BPD, Condensate Refinery 2015-2018 Farzanegan Fars Nikoo Basic Design
 75 PDH Kangan 2017-2018 Oil Industries Engineering Co. (OIEC) Feasibility Study
 74 5 Stations T.C. re-Installastions Qazvin/Khoramdare, Parchin, Semnan, Nizar Qom 3 5 Stations Gas Compressor 2016-2018 Iranian Gas Engineering & Development Co. (IGEDC) Management & Site Supervision for Installation of Spare T.C. of five Stations
 73 South Pars Gas Field Development – Phases 17&18 Assaluyeh 1,000 MMSCFD Natural Gas 2×40,000 BBLS/D Condensate 2006-2016 Pars Oil & Gas Company (POGC)/ OIEC Basic Design Review, Detail Design, Procurement Engineering Services, Field Engineering Services
72 Kian Petrochemical 1395 KTPA Aromatic &2236 KTPA Olefin 2016-2017 Kian Petrochemical  Company Conceptual Study (Cooperation with Axens)
71 North-Northeast Six Gas Compressor Stations 58, 57, 54, 52, 30, 30  MMSCMD 2007 IGEDC MC & SSC
70 Heavy Oil Refinery Production and Lights Bitumen 1000000 TN Bitumen 2015 IPMI Feasibility Study
69 TGTU of South Pars Gas Field Development– Phases 2 & 3, Assaluyeh 2 ´ 130 Ton/day, Liquid sulphur from acid gas TGTU 95% to 99.7% efficiency 2012 (Hold by Owner) Pars Oil & Gas Company (POGC) EPC
68 Tabriz Refinery Gasoline Production Plant, Tabriz 20,000 BPSD 2007-2013 Tabriz Oil Refinery Co. EPCC, Partnership with SEI (China), Construction with TANAVOB
67 Ilam HDPE Plant, Ilam 300,000 t/y, HDPE 2004-2013 Ilam Petrochemical Company EPCC, Partnership with MES (Japan)
66 Mahshahr Jetty No.2 2008-2010 Mahshahr, Petrochemical Special, Economic Zone, Management MC & SSC
65 Hormoz Heavy Oil Refinery 300,000, BBL/D 2008-2012

(Hold by Owner)

NIOEC EPC (as amember of consortium), Part of Utility & Offsite unites
64 Tehran Refinery Products Quality Upgrading Plant 80,000 BBL/D,
De-sulfurization
2007-2012 NIOEC MC & SSC
63 Pars Polystyrene Plant, Assaluyeh

 

250, 000 t/y, Polystyrene 2005-2008 (Hold by Owner) Pars Petrochemical, Company EPCC, Partnership with Simon Carves (UK)
62 Sirri Island, Gas Gathering & NGL Recovery 50 MMSCFD Natural Gas, 6,900 BPD Propane, 3,750 BPD Butane, 3,180 BPD Condensate 2004-2007, (Engineering) IOOC/NIOC Basic Design Review, Detail Design, Procurement Engineering Services, Field Engineering Services
61 Bid Boland II Gas Processing & Pipiline 57 MMSCMD 2007-2012 IGEDC MC & SSC
60 Day & Sepid Zakhur, Gas Field Development 2009-2011 ICOFC MC & SSC
59 Khuzestan Extra Heavy Crude Oil Refinery 180,000, BPSD 2008-2009 NIOEC Basic Design
58 Darquain Oil Field Development-Phase 2 2  ´ 55000, BPSD 2007-2009 PEDEC MC & SSC
57 South Pars Gas Field Development Project, Phases 9 & 10, Bandar Assaluyeh 2 ´ 1,000 MMSCFD Natural Gas 2 ´ 40,000 BBLS/D Condensate 2004-2008 Pars Oil & Gas Company (POGC) FES, Field Engineering Services
56 South Pars Gas Field Development Project – Phases 9 & 10, Assaluyeh 2 ´ 1,000 MMSCFD Natural Gas 2 ´ 40,000 BBLS/D Condensate 2003-2006 Pars Oil & Gas Company (POGC) Detail Engineering and Procurement Engineering  Services, As Engineering Sub-Contractor of OIEC
55 Qom-III  Gas Compressor Station 90 MMSCMD 2004-2006 NIGC Complete Basic Design, Detail Engineering and Engineering Services of Procurement
54 Four Gas Compressor Stations – North West 4 ´ 60  MMSCMD 2006-2007 NIGC SSC, Site Supervision Contractor
53 Six Gas Compressor Station 87,87,90,90, 90,160 MMSCMD 2002-2005 NIGC SSC, Site Supervision Contractor
52 Consulting Services To “MATN” 2005-2006 PEDEC, “MATN” Consulting Engineering Services
51 Acetic Acid Plant, Mahshahr 150,000 t/y, Acetic Acid 2003-2006 Fanavaran, Petrochemical Company FES (Field Engineering Services)
50 7th Olefin Plant, Mahshahr 1,100,000 t/y, Ethylyne 200000 t/y propylene 2001- 2005 Maroun Petrochemical Company (MPC) SSC, Site Supervision Contractor
49 4th Aromatic, Bandar Assaluyeh 750,000 t/y Paraxylene 2002-2005 Borzuyeh Petrochemical Company (BPC) MC, Partnership with Foster Wheeler
48 Petrochemical Storage Facilities Lots of and facilities Storage Tanks 2004-2005 PIDMCO FES, Field Engineering Services
47 Six Gas Compressor Stations 87, 87, 90, 90,90, 160 MMSCMD 2002-2004 NIGC Complete Basic Design, Detail Engineering and Engineering Services of Procurement
46 Acetic Acid Plant, Bandar Imam 150,000 t/y Acetic Acid 2001-2004 Fanavaran Petrochemical Company Detailed Engineering, Procurement and Technical Assistance Services, 29Partnership with GS
45 Petrochemical Storage Facilities, Bandar Imam Lots of and facilities Storage Tanks 2002-2004 PIDMCO Complete Basic Design, Detail Engineering and Procurement Services
44 7th Olefin Plant, Mahshahr 1,100,000 t/y, Ethylene 200,000 t/y, Propylene 2000-2004 Marun Petrochemical Company (MPC) Detailed Engineering, Procurement

Partnership with Linde

43 NGL 1300 180, MMSCFD, of Feed Gas 4400 BBIS/D,of Feed Condensate 1999- 2003 NPC Detailed Design, Procurement Services, Pre-Comm. & Commissioning Supervision
42 NGL 1200 260, MMSCFD, Of Feed Gas 1999- 2003 NPC Detailed Design, Procurement Services, Pre-Comm. & Commissioning Supervision
41 Turkmenbashi Refinery Gasoline unit MSCC, LPG & Gasoline

Merox Units 24,000, BPSD Gasoline

1999-2000 NIOEC Detail Design, and Procurement, Services
40 6th Olefin Plant, Mahshahr 520,000 t/y, Ethylene

154,000 t/y, Propylene

1998- 2003 Amirkabir Petrochemical Company (AKPC) Detailed Engineering , Procurement & Field Engineering Services, Partnership with Linde
39 Noor Abad Gas Compressor Station 86, MMSCMD 2001-2003 OIEC/NIGC Complete Process Basic Design, and Detail Design
38 S3 & S6 Gas Compressor Stations 90MMSCMD, For S3 station, & 62MMSCMD for S6 Sstation 2000-2002 NIGC Basic Design for Civil & Structural Discipline and Complete Detail Engineering
37 Norooz Oil Field Master Development Plan Altern.A 90,000 BFPD Altern

B 120,000 BFPD

1998-1999 Repsol Exploration Pre- Basic Design, for the total Surface Facilities
36 South Pars Gas Field Development Phase 1, Stage 2 1997-1998 PEDEC Detailed Design (Terminated At 50% Progress)
35 Norooz Oil Field Renovation the Persian Gulf Offshore & Onshore 90,000 BBL/D 1997-1998 NIOC Offshore Extended Basic Design
34 Khangiran Gas Treating Plant Phase II, Khangiran Two GTU One SRU & Utility Expansion 1996-1999 NIGC Basic Design Review, Detailed Design, Procurement Services & Technical Support
33 NGL-600 1996-1998 DICE Supervision of Plant Installation
32 Gachsaran Gas Treating and Injection, Gachsaran 1995-1998 NIOC Basic Design Review, Detailed Design, Procurement Services & Technical Support
31 Tehran Refinery Waste Water Treatment

 

1995-1998 Tehran Refinery Optimization Study
30 Sarkhun II Gas Refinery Gas Sweetening Unit 1000 1995-1998 NIGC Basic & Detailed Design Technical Assistance
29 Tabriz Petrochemical Complex, Tabriz HVAC Engineering 1995-1998 Tabriz Petrochemical Complex Detailed Design and Procurement Services
28 Iran Gas Europe Altern. A LNG Altern. B Pipeline, Iran- Europe A:10 LNG Trains each 2.5 million t/y, B: 35 bncm/ySales Gas 1995-1996 Linde Feasibility Study
27 ISO Standards Translation 1995-1996 Plan & Budget, Organization Translation of 137 ISO Standards in to Farsi
26 Norooz Oil Field Living Quarters, the Persian Gulf 1995-1996 NIOC- offshore Basic Engineering
25 Master Development Plan for Kharg, Siri, Lavan Islands, & Bahregan Oil Centre, the Persian Gulf 1995-1996 NIOC- offshore Engineering
24 Foundation of Drilling Rigs, Kharg Island 1995-1996 NIOC- Offshore Engineering & Tech. Support
23 1.33 Million Barrel Crude Oil Storage Tank, Kharg Island 1.33 Million Barrel Crude Oil 1995-1996 NIOC-Offshore Engineering
22 Dorood Oil Field Development in the Persian Gulf 1995-1996 NIOC- Offshore Engineering & Tech. Support
21 Arak Lube Oil Arak 1995 Bonyad Mostazafan Feasibility Study
20 NGL 1200 &1300 Plants, Gachsaran Bibi Hakimeh 1995 NIOC- Onshore Preliminary Engineering Study
19 Pakistan Iran- Pak Refinery 1995-1996 NIOC- PERAK Engineering, Preparation of Tender Document
18 South Pars Gas Field Development (phase-1) 1995-1997 PEDEC Conceptual Study & Basic Design
17 Tehran Refinery, Tehran Modernisation of Control Systems, 1995 Tehran Refinery NIOC Basic Design & Optimization Study
16 Furfural Unit, Tehran Pars Oil Refinery,

Tehran

1994 -1996 Pars Oil Company Contribution in Detailed Design (Renovation & Capacity Increase)
15 Aromatic Unit, Bandar Imam Petrochemical Company, Bandar Imam 1994-1998 BPC Site Activities, Supervision, Technical Services, Field Engineering & Engineering support
14 Esfahan Pipeline River Crossing Bridges Karoon, Jarahi, Zayandehrood River 1994-1997 NIOC Design Of Bridges & River Crossing (Basic & Detailed Design)
13 Sarkhun  Pump Station 12,000, BBL/D 1993-1998 NIGC Basic and Detailed Design Engineering & Technical Assistance
12 Ahwaz Pipeline Facilities Pump Station for Mile 40 Ahwaz & Tabriz Pipeline, Pump Station for Tabriz-Sarab-Ardabil Pipeline Technical Service (200,000 BBL/D) 1993-1995 NIOC Basic and  Detail Design Engineering & Procurement Services, Basic and Detailed Design Engineering & Procurement Services
11 Esfahan Polyacryle Complex, Esfahan Air Pollution Control & Recovery System Optimization of Monomer in Polyacryle Co. 1992-1993

1994-1998

Iran Polyacryle Company Basic and Detailed Engineering.
10 Khoramabad Nyl-Iran Tire Production Co. , Khoramabad 1992-1993 Bank of Industry and Mines of Iran Optimization Study for the Use of Nylon Fibbers in the Tire Industry
9 Tehran Planning & Information System Design Management Services 1992-1994 Hormozgan Cement Co. Design and Development of Project Planning and Controlling System
8 Pakistan/Iran Pak Refinery 1992-1993 ABB Lummus Crest (Germany) Feasibility Studies
7 Ninth (Condensate) Refinery, Bandar Taheri 70,000 BBL/D,  DCS Control, The Refinery Includes DEA Gas Treater 1991-1993 NIOC Complete Basic Design of Condensate Refinery
6 Khorasan Petrochemical Complex, Bojnurd, Khorasan 1990-1991 Khorasan Petrochemical Complex Consultancy Services for the Entire Complex
5 Esfahan Petrochemical Complex, Esfahan 7,500 BPD 1990-1991 Esfahan Petrochemical Complex Basic & Detailed Design of Feed Facilities
4 Arak Refinery, Arak 21,600 BPD, DCS Control 1990-1991 TPL, Italy Detailed Design NHT/CCR Platformer Units
3 L.A.B Complex, Esfahan 12,000 BPD 1988-1991 Iran Chemical Industries Investment Company Basic & Detailed Engineering of Feed facilities Design
2 Iranian Petroleum Standards (IPS) Preparation of Standards in all Related Fields For the Ministry of Petroleum 1988-1996 NIOC 398 Standards With More Than 20,000 Pages in 12 Work Disciplines
1 Bandar Abbas Refinery, Bandar Abbas Two Separate Trains, each 116,000 BBL/D Vacuum Unit Capacity 63,000 BBL/D 1988-1990

1990-1997

Snamprogetti Italy Basic & Detailed Design of Vacuum & Atmospheric Distillation Unit